PLASTER INSPECTION Ensure all the checks ( Brickwork Checklist ) after block work is complied with. The aluminium template for openings (sometimes we use sand to cover the electric holes) should be available at the site. The blockwork should have been cured for 7 days and dry before plastering is started. Button mark the surface to be plastered keeping the minimum thickness. 12mm plaster is the desired thickness. The distance of button marks should be within an aluminium straight edge length. Plastering mesh should be 8” wide and fixed rigidly before plastering on the junction between concrete and masonry surface with steel nails / wooden plug and nails. This strip has to be plastered and cured for a minimum of 3 days before the entire wall is plastered. Get the plastering specifications like lime finish, trowel finish, sponge finish, rough plaster and zone of application clarified from architects. In the case of external plaster grooves, it can be incorpor...